When is the last date that a Payment Claim can be made?

The BCIPA [s17(4) states, A payment claim may be served only within the later of –

(a) the period worked out under the construction contract; or

(b) the period of 12 months after the construction work to which the claim relates was last carried out, or the related goods and services to which the claim relates were supplied.